Pre-Construction Water Hygiene: A Guide for New Builds

2 days ago
9 min read

Unused washbasins in a newly completed school

Pre-construction water hygiene means planning how the hot and cold water systems of a new or refurbished building will be designed, installed, filled, flushed, disinfected and handed over, so that the water is safe on the day people start using it. The work starts at design stage, not at handover. A new building is not automatically free of Legionella: water that sits in new pipework and tanks during construction, delays or phased occupation can grow bacteria before anyone has turned on a tap. This guide sets out what UK guidance expects and what to put in place at each stage.



TL;DR

 

  • Involve water safety at design stage: HSE guidance says design must avoid stagnation, dead legs and components that raise colonisation risk.

  • The period between first filling a system and normal use is potentially the most hazardous, so keep filling as close to occupation as you can.

  • Any new water system needs, at a minimum, flushing and disinfection before use, with sampling to confirm the result.

  • Record decisions in a water safety plan and a risk assessment completed before occupation, with someone named as responsible at each stage.

  • Our Legionella risk assessments and water sampling can support handover.

 

Table of Contents

 

 

Why a new building still carries Legionella risk

 

Legionella bacteria grow in water between roughly 20°C and 45°C when it is not moving. A new building often provides exactly that: pipework pressure tested with water, tanks filled early, outlets nobody uses for months. HSE’s technical guidance HSG274 Part 2 states that, from a microbiological perspective, the period between filling the system and bringing it into normal use is potentially the most hazardous. It also points to buildings that are not fully occupied immediately, or are commissioned as occupation occurs, as a source of stagnation.

 

The consequences can be serious. A 2023 peer-reviewed review in Buildings describes the investigation at the Queen Elizabeth Royal Hospital for Children, which identified 23 confirmed paediatric cases in 2018. The authors link the problem to high water age from early water activation, unsuitable temperatures, dead legs and debris in water tanks, and they conclude that coordination between owners and the design, construction and commissioning teams was lacking.

 

You do not need to run a hospital for this to matter. The same mechanics apply to a school extension, a surgery fit-out or an office floor left empty between practical completion and the tenant moving in. For more on the mechanism, see our guide on why stagnant water causes Legionella.

 

Stage 1: Design and planning

 

The cheapest place to fix a water hygiene problem is on the drawing. HSG274 Part 2 asks the design to identify the water source, and to flag components that increase colonisation risk, such as blending valves and flexible hoses. It also asks designers to consider the potential for stagnation if the building will not be fully occupied straight away.

 

In practice, design checks include:

 

  • Flow through every part of the system. Avoid dead legs, blind ends and redundant connections.

  • Low-use outlets placed upstream of frequently used ones, so water keeps moving past them.

  • Temperatures that do not support growth in storage vessels and pipework, which means thinking about where hot and cold pipes run together.

  • Hot-water-rated check valves with anti-gravity loops where backflow protection is needed.

  • Energy-efficiency measures assessed so that Legionella control is not compromised by lower storage temperatures or reduced circulation.

 

In healthcare, HTM 04-01 Part A says the Water Safety Group should be consulted at the earliest possible opportunity when premises are planned, altered or refurbished, and that water risk assessments should be completed for all projects. Our HTM 04-01 guide explains what that means for healthcare estates.

 

Notify the water undertaker

 

Under the Water Supply (Water Fittings) Regulations 1999, HTM 04-01 Part A states that design teams and installers must notify the water undertaker and obtain consent before installation begins. Installing or using fittings without prior consent is an offence. Build this into the programme early, because consent timing can hold up the start of installation.

 

Stage 2: Construction controls

 

Contamination on site is the quieter half of the problem. HTM 04-01 Part A sets out practical controls for installers:

 

  • Keep tools and clothing used on sewerage and drainage work separate from hot and cold water work.

  • Use only components that have been stored hygienically and are inspected as clean and free of defect before installation.

  • Prevent debris or contamination entering pipework, tanks and fittings during works.

  • Flush and disinfect where contamination is suspected.

  • For new builds and refurbishments, the contractor is responsible for making sure everyone working on the water system has completed water hygiene training.

 

NHS England’s NETB 2024/3, issued in August 2024 as a supplement to HTM 04-01, says a water safety plan should be followed throughout the project to prevent opportunistic pathogens entering at every stage. It treats high-risk processes in the life of a water system as a continuing source of colonisation, not one-off events. It also says systems should be operated with disinfected water through point-of-entry filtration. The bulletin is written for NHS settings, but the logic is sound for any building with vulnerable occupants.

 

On-site awareness matters as much as paperwork. Our Legionella awareness training is available on-site and online, which suits a project team that changes through the programme.

 

Stage 3: Filling, pressure testing and delays

 

Pressure testing is where many new systems first meet water. The Leicester University water safety plan, written for its own estate, requires that the first water entering a new system is clean and fit for use. It specifies flushing, sampling and, where needed, disinfection of the incoming supply immediately before first fill for pressure testing. It also asks for the local water supplier to be consulted on a plan for filling, flushing and disinfection water. You can read it in the University of Leicester water safety plan.

 

If a long gap is likely between pressure testing and occupation, HSG274 Part 2 describes the controls: weekly flushing, temperatures kept below 20°C for cold water, and maintained residual disinfectant levels. Systems that are drained down after wetting can also develop biofilm in residual water pockets, so avoid draining down unless full disinfection is planned afterwards.


Four controls for water systems during delays

The practical lesson: fill late. The longer water sits in a system before use, the more you rely on flushing regimes and monitoring to compensate. Where occupation is phased, consider automated water temperature monitoring so that temperature drift in unused parts of the building is visible without a weekly site visit.

 

Stage 4: Commissioning, disinfection and sampling

 

HSG274 Part 2 states that any new water system requires, as a minimum, flushing and disinfection before it is brought into use. It adds that a correctly designed and installed system should deliver wholesome water at every outlet, and that defects should be identified and rectified where problems occur.

 

For larger projects, the Leicester plan gives a useful working pattern:

 

  1. Disinfect as soon as practicable after filling and as close to handover as possible, by shot-dosing a suitable disinfectant within the limits in BS EN 806-4:2010 and BSI PD 855468:2015.

  2. Do not drain the system after disinfection unless full disinfection will be repeated before occupancy.

  3. Flush in a way that mimics normal use between disinfection and handover, including TMVs, showers and little-used outlets.

  4. Allow at least three weeks after disinfection for sampling results to come back, with no more than 30 days between disinfection and handover.

  5. If 30 days is exceeded, repeat the agreed handover sampling in addition to the original sample set.

 

These intervals come from one organisation’s own plan, so use them as a sound reference point and agree the figures for your project in the commissioning method statement. Small developments with simple systems, such as individual commercial units or small offices, are treated more simply: HSG274 Part 2 says they should be thoroughly flushed before use, as close to occupation as possible.

 

What sampling can tell you

 

Sampling before handover gives you a dated, laboratory-backed record that the system was clean at the point of occupation, and it flags problems while the contractor is still on site to fix them. Our Legionella water testing and analysis service starts from £55 per sample, and we can also test for Pseudomonas aeruginosa, total viable count and potable water quality where your specification asks for it.


Technician collecting a water sample at a tap

Tanks and TMVs

 

Cold water tanks are a frequent source of trouble in new buildings, because debris can enter during construction. Tank cleaning and system disinfection is a routine part of preparing for handover, and thermostatic mixing valves need to be commissioned and then serviced regularly. We cover both, together with water tank cleaning and disinfection and TMV servicing and remedial works.

 

Who is responsible at each stage

 

Responsibility is where new-build projects most often come apart. A few reference points from UK public bodies show the pattern:

 

  • Persons commissioning works. Broxtowe Borough Council’s Legionella policy states that those commissioning works to water systems are directly responsible for ensuring Legionella risks are considered at design, and that a water systems risk assessment is carried out for new buildings before use.

  • Mechanical contractor. The Leicester plan requires the mechanical services contractor to draft a detailed commissioning method statement aligned with the water safety plan. It covers design temperatures, chemical levels, flow rates, pressures, TMV commissioning, sentinel monitoring points, test certificates and a risk assessment to BS 8580:2019.

  • Duty holder. Under HSE’s L8 Approved Code of Practice, the person who controls the premises must manage the risk once the building is in use, which means the handover pack has to give them what they need.

 

Write the names down. A handover is only as good as the person who receives it and understands what the documents mean.

 

A practical handover checklist

 

Item

What to have in hand

Design review

Drawings checked for dead legs, stagnation, low-use outlets and components of concern

Water undertaker consent

Notification and consent under the Water Fittings Regulations 1999

Installer training

Records that operatives completed water hygiene training

First fill

Evidence of flushing and, where required, disinfection of incoming supply

Disinfection

Dosing records, contact times and results

Flushing log

Regular flushing that mimics normal use until handover

Sampling

Laboratory results from agreed points, dated within the agreed window

Risk assessment

Legionella risk assessment completed before occupation

Operating records

Logbook, temperature regime and named responsible person

Our method of works page explains how we document and carry out compliance work on site.

 

Special cases: healthcare, schools and housing

 

Buildings with vulnerable occupants need extra care because the consequences of colonisation are greater. For healthcare premises, see our page on Legionella compliance for healthcare premises and our article on immunocompromised patients. Education estates often have long holiday shutdowns that interact with phased handovers, which we cover under schools, colleges and universities. Housing providers can find examples in Legionella prevention in social housing.

 

Our perspective

 

Most of the problems we are asked to fix in new buildings were avoidable on paper. The water was filled early, the programme slipped, nobody owned the flushing, and the first time anyone looked at the system was after handover.   Our view is simple. Treat water hygiene as a workstream with its own owner, its own records and its own sign-off, from design to occupation. A risk assessment before people move in, sampling that confirms the system is clean, and a logbook the building team can actually use do more than any amount of reassurance later.   That is why we build our services around the site. Risk assessment, water sampling, tank cleaning and disinfection, TMV work, training and ongoing support are designed to fit together, so that the handover pack answers the questions the duty holder will ask on day one.   Sammi

 

Getting your project ready for handover

 

If you are planning a new build, extension or refurbishment, we can carry out a Legionella risk assessment (from £185), arrange water sampling, clean and disinfect tanks and systems, and provide ongoing support once the building is in use. Our work covers sites across the UK and we aim for rapid turnaround on quotes and reports.

 

[


Bespokecompliancesolutions

 

To discuss a project, start from our main site and tell us the stage you have reached and the handover date you are working towards.

 

FAQ

 

Does a brand new building need a Legionella risk assessment?

 

Yes. Council and healthcare policies state that a water systems risk assessment should be completed for new buildings before use or occupation. It should reflect the as-built system, not just the design, and the person commissioning the works is responsible for making sure it happens.

 

How long can a new system sit filled before occupation?

 

There is no single figure for every building. HSG274 Part 2 treats the gap between filling and use as potentially the most hazardous period, and sets controls for long gaps: weekly flushing, cold water below 20°C and maintained disinfectant residuals. Aim to fill as close to occupation as possible.

 

Do new systems need disinfecting?

 

HSG274 Part 2 says any new water system requires, as a minimum, flushing and disinfection before it is brought into use. Small, simple systems such as individual commercial units need thorough flushing as close to occupation as possible.

 

Do we need to tell the water supplier about new pipework?

 

Yes. Under the Water Supply (Water Fittings) Regulations 1999, installers must notify the water undertaker and obtain consent before installation commences in the cases the regulations cover. HTM 04-01 Part A notes that installing fittings without prior consent is an offence.

 